Application Reports
|
|
90 Ton Aluminum Round Melter - Permanent Cast Veneer Hot Face Repair |
Conventional refractory sidewalls were worn out and repairs were required. Normally repairs would be a full rebuild of sidewalls requiring 4 weeks of downtime. Customer could not afford this down time. Solution was to leave existing conventional floor alone and tear outside wall. Repair complete circumference of sidewall using Thermbond Formula 4-L from belly band to floor |

|
|
Aluminum Melting Holding Pouring Furnace - Casting |
Due to high operating temperatures, dross builds up very badly and reduces furnace capacity in this aluminum furnace.
Perform a total reline using Thermbond products. |

|
|
Anchorless Permanent Veneer Repair, Aluminum Furnace - Casting |
Refractory failed prematurely because of damage from mechanical cleaning, use of aggressive cleaning fluxes, moisture pickup and frequent cycling from hot to cold.
Overlay a veneer of Thermbond. This lining would allow the customer to avoid the capital expenditure of a new lining. Thermbond would also protect against corundum growth and eliminate the need for aggressive cleaning fluxes, and provide longer lining life that required less maintenance. |

|
|
Atomizer Furnace Sidewalls, Roof and Hearth - Gunning |
Furnace produces a powder which is used to make the fuel for the Space Shuttle. Existing refractory deteriorated from penetration and mechanical abuse. |

|
|
Premier UAE Primary Smelter, Casting |
Heavy erosion on lintels, side jambs, sil, side walls, roof and burner throat. |

|
|
Relining of Holder and Melter in Dubai, UAE |
Both furnaces had to be repaired in less than 20 days.
Fast setting and tenacious chemical bond capabilities of Thermbond products solved the customer’s problem by enabling them to repair rather than replace, and heat up the lining much faster than conventional refractories. |

|
| Round Top Aluminum Melting Furnace |
Refractory belly band was worn out due to chemical and mechanical attack. |
 |
|
Wheel Casting Facility, Aluminum Furnace - Cast |
The conventional refractory on the wall of the reverb furnace was worn past its serviceable life. The burner wall collapsed and the remaining refractory was completely removed for rebuild. The original conventional cast materials only lasted one year. Stellar cast Thermbond, which cured faster, heated up faster, and required less maintenance. Thermbond also delivered extended service life. |

|
|
Wheel Casting Facility, Aluminum Furnace - Gunned |
The conventional refractory on the wall of the reverb furnace was worn past its serviceable life. The burner wall collapsed and the remaining refractory was completely removed for rebuild. The original conventional cast materials only lasted one year. Stellar gunned Thermbond, which cured faster, heated up faster, and required less maintenance. Thermbond also delivered extended service life. |
 |